Next week, on Wednesday 9th August at 11am, we will be holding a Resident Liaison Meeting and would like to extend the Milliners Wharf Residents that would like to attend.
The meeting will be held in the site meeting room cabin and will be a chance for residents to get an update on the project, ask questions and raise any concerns that they may have. Space is limited however and will be on a first come, first serve basis so please contact us via the “Get in Touch” tab and fill in the form at the bottom of the page. Equally, this form can also be used if you cant attend, but still have questions. All questions raised will be discussed and the outcome be posted on this website for everyone to access.
This will also give us the perfect opportunity to introduce our new team members as we have a new Resident Liaison Officer and a new Site Manager that have recently become involved in The project.
As always, feel free to get in touch if you have any questions about any of the above. You can either use the contact page on the website or simply call into the site office and speak to a member of the team.
Hi,
Would it be possible for you to share with the leaseholders, the progress % made so far, the scheduled remedial time table and projected completion time.
I have requested for the above information several times in the past but have not seen any update yet
Hi Mosi,
Progress is currently at around 45/50% with the project scheduled to be complete in early 2023.
In around 2 months time, works to the canal side of the building will be complete and all remaining works will just be focussed around the car park elevation.
If there is a particular area that you would like more info about, please just let us know and we will help where we can.