Meeting/Project Name: Milliners Wharf Resident Liaison Meeting Date of Meeting: 13/09/2023 Time: 11:00 Minutes Prepared By: Adam Prescott Location: Site Meeting Room Attendance at Meeting Adam Prescott (AP) - Intelligent-FS Colin Halligan (CH) -...

millinerswharf@intelligent-fs.
Meeting/Project Name: Milliners Wharf Resident Liaison Meeting Date of Meeting: 13/09/2023 Time: 11:00 Minutes Prepared By: Adam Prescott Location: Site Meeting Room Attendance at Meeting Adam Prescott (AP) - Intelligent-FS Colin Halligan (CH) -...
Next week, on Wednesday 9th August at 11am, we will be holding a Resident Liaison Meeting and would like to extend the Milliners Wharf Residents that would like to attend. The meeting will be held in the site meeting room cabin and will be a chance for residents to...
Since our last update, we have had lot happening on site. In this post, we will give a run down of the works completed and the works planned in the coming weeks. Using the diagram above as a guide, below is a summary of the progress made so far in each position....
We would like to advise that core 2 entrance will be closed off on Monday 10th July and that we will require car park spaces 106 and 107 clearing to install back propping for mast climbers.
The past few weeks on site have seen an increase in the number of operatives as well as an increase in the pace of the work being carried out. Last week we have had 25 people on site and this has helped to keep up the momentum and push works forward. Below is a brief...
What Are We Doing? We're sure that this is a question a lot of people are asking as they begin to see works progress around the building, so we thought we would use this update to breakdown each stage of the work that we are carrying out and give a bit of an insight...
Midway through our fourth week back on site, we are starting to build up momentum with the number of operatives increasing weekly. We currently have 3 live work areas on the 2 mast climbers along the canalside and the Carruthers St elevation. In these areas, we have...
In the pre-Christmas update back in December, we mentioned that we would be aiming to re-commence work in mid-January. This is now confirmed to be as of this Monday (16th Jan) when we will install the access requirements to Phase 2 and work on the scaffold on the...
As well as the cladding remediation project, there are a number of other smaller works that Intelligent FS will be undertaking whilst onsite at Milliners Wharf. One of these smaller work areas will be investigations into the roof and, in particular, trying to find the...
Due to the number of comments and queries that we have received lately regarding the lack of progress on the project, we thought it would be best to issue a further update as to the current status of the cladding remedial works. Due to the building being a live...