Progress

What Are We Doing?

What Are We Doing?

What Are We Doing? We're sure that this is a question a lot of people are asking as they begin to see works progress around the building, so we thought we would use this update to breakdown each stage of the work that we are carrying out and give a bit of an insight...

read more
8th Feb Project Update

8th Feb Project Update

Midway through our fourth week back on site, we are starting to build up momentum with the number of operatives increasing weekly. We currently have 3 live work areas on the 2 mast climbers along the canalside and the Carruthers St elevation. In these areas, we have...

read more
Works Re-Commencing 16th January

Works Re-Commencing 16th January

In the pre-Christmas update back in December, we mentioned that we would be aiming to re-commence work in mid-January. This is now confirmed to be as of this Monday (16th Jan) when we will install the access requirements to Phase 2 and work on the scaffold on the...

read more
Roof Investigations

Roof Investigations

As well as the cladding remediation project, there are a number of other smaller works that Intelligent FS will be undertaking whilst onsite at Milliners Wharf. One of these smaller work areas will be investigations into the roof and, in particular, trying to find the...

read more
General Update

General Update

Due to the number of comments and queries that we have received lately regarding the lack of progress on the project, we thought it would be best to issue a further update as to the current status of the cladding remedial works. Due to the building being a live...

read more
Project Update 03/10/2022

Project Update 03/10/2022

Works Update Since the last project update, we have been working through a lot of initial site set up and survey/investigation works.  Site infrastructure has been set up including all welfare facilities and temporary power requirements for site plant.  Double...

read more
Drone Dilapidation Survey

Drone Dilapidation Survey

On 30th August a drone survey of the building was carried out. This is to create a detailed record of the condition of the building before any works commence. By doing this, we can clearly see if any damage has been cause during the cladding works and this ensure that...

read more
Site Set Up

Site Set Up

The initial site set up commenced 22nd August with site offices and welfare being delivered as well as the site boundary being established. This area will be the main hub of the project for the site team and will remain in place for the duration of the works. It was...

read more