by Adam Prescott - Intelligent-FS | Dec 14, 2022 | Latest News, Progress
As well as the cladding remediation project, there are a number of other smaller works that Intelligent FS will be undertaking whilst onsite at Milliners Wharf. One of these smaller work areas will be investigations into the roof and, in particular, trying to find the...
by Adam Prescott - Intelligent-FS | Nov 11, 2022 | Latest News, Progress
Due to the number of comments and queries that we have received lately regarding the lack of progress on the project, we thought it would be best to issue a further update as to the current status of the cladding remedial works. Due to the building being a live...
by Adam Prescott - Intelligent-FS | Sep 6, 2022 | Latest News
Wednesday 7th September will see the first area of scaffold erected on the project; this will be to the Carruthers Street side of the building. This scaffold will initially be used as access for inspections with the consultants to determine the current state of the...
by Adam Prescott - Intelligent-FS | Aug 30, 2022 | Progress
On 30th August a drone survey of the building was carried out. This is to create a detailed record of the condition of the building before any works commence. By doing this, we can clearly see if any damage has been cause during the cladding works and this ensure that...
by Adam Prescott - Intelligent-FS | Aug 30, 2022 | Progress
The initial site set up commenced 22nd August with site offices and welfare being delivered as well as the site boundary being established. This area will be the main hub of the project for the site team and will remain in place for the duration of the works. It was...