April Project Update

April Project Update

The past few weeks on site have seen an increase in the number of operatives as well as an increase in the pace of the work being carried out. Last week we have had 25 people on site and this has helped to keep up the momentum and push works forward. Below is a brief...

read more
What Are We Doing?

What Are We Doing?

What Are We Doing? We're sure that this is a question a lot of people are asking as they begin to see works progress around the building, so we thought we would use this update to breakdown each stage of the work that we are carrying out and give a bit of an insight...

read more
8th Feb Project Update

8th Feb Project Update

Midway through our fourth week back on site, we are starting to build up momentum with the number of operatives increasing weekly. We currently have 3 live work areas on the 2 mast climbers along the canalside and the Carruthers St elevation. In these areas, we have...

read more
Works Re-Commencing 16th January

Works Re-Commencing 16th January

In the pre-Christmas update back in December, we mentioned that we would be aiming to re-commence work in mid-January. This is now confirmed to be as of this Monday (16th Jan) when we will install the access requirements to Phase 2 and work on the scaffold on the...

read more
Final Update of the Year

Final Update of the Year

As we edge closer to the end 2022, we begin to look forward to what 2023 will bring. For the Milliners Wharf project we expect a busy year with the works kick starting again and building the momentum that will drive us to completion, and along with it creating safe...

read more
Roof Investigations

Roof Investigations

As well as the cladding remediation project, there are a number of other smaller works that Intelligent FS will be undertaking whilst onsite at Milliners Wharf. One of these smaller work areas will be investigations into the roof and, in particular, trying to find the...

read more
General Update

General Update

Due to the number of comments and queries that we have received lately regarding the lack of progress on the project, we thought it would be best to issue a further update as to the current status of the cladding remedial works. Due to the building being a live...

read more
Project Update 03/10/2022

Project Update 03/10/2022

Works Update Since the last project update, we have been working through a lot of initial site set up and survey/investigation works.  Site infrastructure has been set up including all welfare facilities and temporary power requirements for site plant.  Double...

read more
Carruthers Street Scaffold Erection

Carruthers Street Scaffold Erection

Wednesday 7th September will see the first area of scaffold erected on the project; this will be to the Carruthers Street side of the building. This scaffold will initially be used as access for inspections with the consultants to determine the current state of the...

read more
Milliners Drone Survey – Wednesday 24th Aug

Milliners Drone Survey – Wednesday 24th Aug

One of the first deliverables of the project is a dilapidation survey of the exterior cladding of the building. This provides an initial view of the condition of the building and provides a baseline for budget planning for any potential cladding panels replacements...

read more